The agreement is put on paper too late
The extra work is approved on site and only formalised days later — or never. What you then have is a one-sided document drawn up after the fact.
VIDIMUS/CASE FILES/CONSTRUCTION & CONTRACTORS
The classic construction dispute: extra foundation work, a moved wall, heavier beams — approved by phone or on site, carried out properly, and at the final account: "we never asked for that." This page sets out what you can do today, what the law says, and what changes when the agreement is fixed at the moment itself and can no longer be changed.
Block B, foundation slab. The client: "Go ahead with that extra reinforcement, it will be fine." Four weeks later, final account: €38,500 in extra work. Answer: "Never approved. Show me the document." There is a three-word text message and an invoice drawn up after the fact.
The extra work is approved on site and only formalised days later — or never. What you then have is a one-sided document drawn up after the fact.
Your site report comes from your system, which you can adjust yourself. For the court, that counts as "your version", not as fact.
Under a fixed-price construction contract, you can in principle only charge extra for additional work if the client agreed to it in writing. Without that proof, you are left with the bill.
Under a fixed-price construction contract, the contractor cannot charge extra for changes or additions unless they were authorised in writing and the price was agreed with the client. Courts sometimes read this more flexibly if the agreement is established in another way — but the risk lies with you.
Between businesses, evidence may be given by any means: emails, photos, a system's history and digital agreements are admissible — the court weighs them. The more independent the evidence, the more weight it carries.
Parties can agree in advance which records count as proof between them, without prejudice to the right to prove the contrary. Such a clause may not unreasonably limit the other party's means of evidence (Code of Economic Law, Art. VI.91/5, 7°). An evidence clause turns an anchored extra work order into an agreed means of proof.
General information, not legal advice. Vidimus provides evidence; how much weight it carries is for the court to assess — and that weight is exactly what anchoring increases.
Six disputed extra work items a year × 8 hours of discussion × €75 = €3,600 in lost hours — plus the extra work you end up dropping to save the relationship. Recording an extra work item is one record: free up to 100 a month, then €0.08.
It is admissible evidence (between businesses, evidence may be given by any means), but it is thin: no amount, no description, and the counterparty often disputes the context. A signed, anchored order with amount and moment carries fundamentally more weight.
No. They sign on your phone or via a link; they receive the order and the verification link themselves. Nothing to install.
Then stricter rules of evidence apply towards the consumer (above €3,500, a written document is in principle required). An order signed electronically by both parties is a written document — that is exactly the point.
You create your account in two minutes. No payment details needed. A director identifies your company once with the Belgian eID; then you create your first logbook in a few minutes. The first 100 records a month and the first measurement source are free. After that, you pay per record or per measurement source, with a minimum of €19 a month.